January 26, 2026
Next week look-a-head
• On Monday, Jan 26, Leighton will continue work across the Gas Bar parking lot toward
the existing septic treatment tanks. They anticipate 3–4 days to complete the sleeve
installation and backfill.
• Access will be kept as open as possible for Co-op customers. One pedestrian crossing will
remain open at all times.
• The final section of trenching will require a temporary closure of the south entrance to
the parking lot (tentatively Jan 29–30). The gas station is expected to remain open
throughout.